How to plan the preventive maintenance for several years?

How to plan the preventive maintenance for several years?

The events are not all generated when the preventive maintenance is approved. The events are rescheduled daily according to a set of rules. The following rules:
  1. Events based on the recurrence: 
    1. If the preventive has a daily plan, a maximum of 2 years are scheduled
    2. If the preventive has a daily plan, a maximum of 2 years are scheduled
    3. If the preventive has a monthly plan with recurrence up to 12 months, a maximum of 4 years are scheduled
    4. If the preventive has a monthly plan with recurrence between 12 and 14 months, a maximum of 4 years are scheduled
    5. If the preventive has a monthly plan with recurrence higher than 24 months, a maximum of 10 years are scheduled
  2. Events based on meters: in this case, the event interval result is used as reference divided by the meter average, to define the events recurrence.
    1. If the events recurrence is up to 7 days, a maximum of 2 years are scheduled
    2. If the events recurrence is between 8 and 365 days, a maximum of 4 years are scheduled
    3. If the events recurrence is between 366 and 730 days, a maximum of 8 years are scheduled
    4. If the events recurrence is higher than 730 days, a maximum of 10 years are scheduled
  3. Events based on recurrences and meters: 
    1. The limit date is defined based on the rules set for the recurrence or to the meters. The event interval selects the set of rules to be applied.
The rules presented will be applied when approving and to each recalculation, that is, to each recalculation the new events will be generated.
    • Related Articles

    • How to set the preventive maintenance plan replacement?

      On the maintenance plans of a preventive maintenance, it is possible to select the replacement criteria. The replacement criteria can be the following: None main (Multiplier) Replacement The plan replacement rules are the following: All maintenance ...
    • How to join plans on the preventive maintenance?

      When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...
    • How does preventive maintenance rescheduling work?

      Preventive Maintenance events recalculation is a daily process that recalculates all preventive Maintenance events. This recalculation can be performed automatically or upon request by the user. O calculate it automatically, you must access the ...
    • How to create a preventive maintenance?

      Preventive maintenance specifies a set of maintenance actions to be performed based on a fixed recurrence or on meter values. To create a new preventive maintenance, select the option Work | Preventive Maintenances: The list of preventive ...
    • How to define the execution of maintenance plans?

      Each maintenance plan of the preventive maintenance has a scheduling configuration. The scheduling can be defined using: Recurrence; Meter; Recurrence and Meter Recurrence The scheduling by each plan's recurrence supports three configuration types: ...