How to add maintenance plans to the work order?

How to add maintenance plans to the work order?

To add a maintenance plan to a work order, you must access the work order file and open the tab "Maintenance Plans":
  1. The list of additional maintenance plans  associated to the work order is presented
  2. On the list, press the button "+" to add one or more maintenance plans.
The task associated to the maintenance plan directly associated. To see the task list, press the additional option of the Maintenance Plan row, on the option Tasks. 

A work order cannot have repeated maintenance plans

    • Related Articles

    • How to create a work order?

      The Work Order (WO) is the entity that represents the maintenance job to be performed and which asset, location or route it refers to. ​ To create a new Work Order, select the option "Work | Work Orders"; The list of work orders will be displayed; ...
    • How to join plans on the preventive maintenance?

      When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...
    • How to assign technicians to the work order?

      When a work order is on a state that allows to assign technicians, it is possible to assign technicians to the work order. To assign technicians, you must access the work order (WO) file you with to perform the assignment to "Work | Work orders", ...
    • How to report labor associated with the work order?

      When a work order is in a state that allows to record costs, it is possible to record labor costs. To record the labor costs, you must access the work order file that you wish to record the costs "Work | Work Orders", select the WO you wish to record ...
    • How to report consumptions associated with the work order?

      When a work order is in a state that allows to record costs, it is possible to record  material consumptions. To report material consumptions, you must access the work order file you wish to report the costs to "Work | Work Orders ", select the WO ...